‘Marathon’ bridge build completed on HS2

Grant Prior 1 year ago
Share

Contractors on HS2 have completed a ‘marathon’ bridge build at Streethay near Lichfield involving 18 specialist construction companies.

Work involved excavating 14,000 tonnes of earth, building a 140 metre retaining wall and moving a 2,600 tonne bridge deck 130 metres into place under the South Staffordshire freight railway.

The work was carried out during a 10 week blockade. It was completed by HS2’s civils contractor in the West Midlands, Balfour Beatty VINCI, and designers Mott MacDonald as part of a Design Joint Venture with SYSTRA (MMSDJV), together with teams from 18 specialist supply chain companies.

At the end of July, the 2,600 tonne bridge deck, which had been cast on land adjacent to the railway was moved 130 metres into position using self-propelled modular transporters.

Since then, each side of the bridge was backfilled, the rail tracks were reinstated, with the railway line was successfully handed back to Network Rail last week and now reopened.

The 25 metres long and 18 metres wide Streethay overbridge sits within HS2’s Streethay cutting and will enable HS2 trains to travel under the existing railway between Birmingham and Crewe.

Through design development, Mott MacDonald engineers were able to reduce the total length of wall structures for the railway at Streethay from 1.6 kilometres to 420 metres, meaning 80% less concrete is needed – saving around 420,000 tonnes of carbon, supporting HS2’s ambition to cut carbon on the project.

The Streethay bridge sits on top of the larger 420 metre long retaining wall structure which will have two additional bridges crossing it – the south bound A38 slip road bridge, and the Rykneld Bridge which carries the A38 north bound slip road and the A38 north and south bound carriageway.

At its peak, over 150 people worked on the complex construction operation, with teams from 18 specialist companies, delivering design, surveys, piling works, bridge build, concrete pouring, crane operations, reinforcements, modular transportation, track and systems removal and reinstatement.

The work was delivered in parallel to the construction of the nearby Fulfen Wood bridge, which involved moving a giant 6,200 tonne single span structure under the West Coast Main Line – the UK’s heaviest drive to install an intersection bridge.

David Millar, Rail Interface Manager at Balfour Beatty VINCI said: “The successful delivery of this complex and challenging piece of engineering near Lichfield is another proud moment for Balfour Beatty VINCI on the HS2 project.

“It’s only been possible thanks to the skill, dedication and support shown by the project team over the past few years, including our supply chain. Together, we’ve had to work around existing transport infrastructure, including the South Staffordshire freight railway and the A38, making this achievement even more rewarding.”

Prior to the railway blockade, retaining walls were installed on either side of the railway, enabling the areas to be excavated. The bridge deck was constructed on land adjacent to the existing railway, 130 metres from its final position.

Once the railway was closed to freight trains, the track and embankment were removed. Bachy Soletanche Balfour Beatty Ground Engineering joint venture then installed an additional 76 secant piles measuring 1.3 metres diameter and 30 metres deep, linking to the piles they installed prior to the blockade, to create two retaining walls which act as the walls for the bridge.

A concrete capping beam was installed over the retaining walls, then the bridge was moved into place using self-propelled modular transporters with 344 wheels. Concrete was poured to attach the deck to the capping beam, the embankment was back filled using 2,500 tonnes of structural backfill, on either side of the bridge, before the railway line was reinstated.

The 18 companies which delivered the project were:

  • J. Murphy & Sons constructed the bridge deck and the concrete elements during the blockade
  • Bachy Soletanche Balfour Beatty Ground Engineering JV (SB3) undertook all piling works, both before and during the blockade
  • The bridge parapets were made by Explore precast
  • Podtrak and RSS Infrastructure delivered rail systems work
  • Balfour Beatty VINCI delivered earthworks
  • Pile break-down was by Pile Breaking Systems UK Ltd
  • Trackway supplied by TPA
  • Jacking the structure and modular transportation by Mammoet UK
  • Survey works track monitoring by Aecom
  • Crane supply by King Lifting supported by BBV lifting teams
  • Concrete provided by CEMEX
  • Reinforcement by ROM – specialist reinforcement manufacturers
  • Temporary works by RMD
  • Permanent works design by Design JV (Mott Macdonald and Systra)
  • Temporary works design by Taylor Woodrow

Latest news

Wates boss returns after collapse of his own contractor

Paul Nicholls was head of the failed Real construction group
6 hours ago

New Fair Payment Code goes live today

Latest bid to get subcontractors and suppliers paid within 30 days
10 hours ago

Lincolnshire concrete supplier files administration notice

Ever Readymix Concrete & Screed operates three depots and a fleet of 20 trucks
10 hours ago

Graham lands first deal on Liverpool’s largest brownfield site

Contractor bags infrastructure package on 10.5 hectare site
1 day ago

Bouygues UK boss to step down

Fabienne Viala to leave after eight years at the helm
1 day ago

Galliford Try scoops £87m brace of London jobs

Firm will redevelop a prominent corner building on Sloane Street in Chelsea
10 hours ago

New HS2 boss Mark Wild starts amid prep for final TBM drives

Former Crossrail CEO starts with a sharp focus on controlling costs
1 day ago

Ten consultants land Thames Water major upgrade places

Firms will share £400m of fee work over next five years
1 day ago

Rayner ultimatum to fix all unsafe tall buildings by 2029

Recladding work must start on all 18m+ resi buildings by 2027
1 day ago

ISG administrator finds just £35m to pay down £1.1bn debt

Failed firm was set to report £148m blackhole from legacy jobs
1 day ago

Redesign needed on Colas “bridge to nowhere”

Technical challenges continue as £38m scheme faces further delays
1 day ago

Skanska UK shakes-up boardroom team

Four new board appointments as two directors step down
1 day ago

Ultra rich clamour for Mace super prime resi scheme

Topping out at £2bn 1 Mayfair scheme where homes start at £35m
1 day ago

Watkin Jones wins £48m St Helen’s affordable homes deal

Firm to build nearly 300 homes for housing association
1 day ago

Barratt sets start date for High Barnet station scheme

Latest scheme to be delivered by the £1.9bn West London Partnership
1 day ago

Investors lose £26m after M&E contractor goes under

78 private investors hit by Gallant Building Services collapse
4 days ago

First contractor call for £80bn Government mega-framework

Seven-year deal will cover construction work across all departments
5 days ago

Transport Secretary quits Cabinet

Louise Haigh resigns over stolen mobile phone revelations
4 days ago

NHS modular specialist looks to strike deal with creditors

Catfoss Group Manufacturing applies for Company Voluntary Arrangement
4 days ago

Kier bags £23m Cheadle Eco Business park job

Contractor beats rival Galliford Try to deliver Stockport council's green business park
4 days ago

Willmott Dixon wins £24m Leeds council housing scheme

Firm will build 82 council houses on site of Hough Top school
4 days ago

Welding crisis road bridges revealed

Bridge projects in Midlands, Gateshead and Cornwall impacted
5 days ago

£1bn Bishopsgate Goodsyard phase one go-ahead

London Mayor approves 550,000 sq ft office scheme above Shoreditch station
5 days ago

Costain poised for major HS2 tunnel fit out deal

Latest major deal on project due imminently
5 days ago

New builds overtake refurbs in London office market

Drop in new construction starts but developers remain bullish
5 days ago

Willmott Dixon wins £23m net zero Surrey SEND school

Hopescourt School job takes low carbon work pipeline to £1.4bn
5 days ago

£1.6m fine after mast climber crush tragedy

Court hears how worker died while unloading work platform
5 days ago

Severfield welding crisis hits five National Highways bridges

Full penetration butt welds under scrutiny as weight restrictions imposed
6 days ago

HS2 awards £3bn of track contracts

Ferrovial BAM and Colas Rail among 'rail systems' winners
1 week ago

Chinese diggers face 83.5% duty after JCB dumping complaint

Fair trade body finds UK kit prices were undercut by 23%
6 days ago

Contractor services