Inquiry warns hospital build programme in disarray

Aaron Morby 1 year ago
Share

The Public Accounts Committee has no confidence that Government will deliver the new hospitals it promised.

In a highly critical report published today, the PAC voices extreme concern at the New Hospital Programme’s lack of progress.

It warns the recently revised target to construct 32 new hospitals by 2030 rather than 40 as first planned is unlikely to be met.

The Committee says that delays to Hospital 2.0 have eaten into the time available to pilot new standardised designs in real-life scenarios running the risk of baking-in and replicating design and construction problems across England.

The PAC report highlights that most worryingly of all, the latest version of Hospital 2.0 is based on assumptions that appear very likely to produce hospitals that are too small.

Delays to signing off standardised design principles has also hindered meaningful engagement with the construction industry on the details of the design and the commercial pipeline of work.

Dame Meg Hillier MPm chair of the PAC, said that big questions remain to be answered about the industry’s capacity and appetite to build the required number of hospitals in the new way and to a very tight timetable.

It also challenges the plan to bolt the rebuilding of seven RAAC impacted hospitals on to the back of the revised programme risks some hospitals having to close before replacements are ready.

“The physical edifice that is the NHS is quite literally crumbling before our eyes. There was nothing inevitable about this heartbreaking crisis.

“It can be laid squarely at the door of the decision to raid budgets reserved for maintenance and investment in favour of day-to-day spending.

“The sharp distinction between capital and revenue budgets exists for a reason. We are now seeing the consequences of this short-termism visited on patients and services.”

She added: “Quite aside from the fact that the planned new hospitals risk being too small for future purposes, funding does not even appear to be in place to construct them in time, all underpinned by failures of basic record-keeping and fresh and urgent concerns over RAAC.

“Though we have no confidence that the NHP will deliver on its current promises, we hope that the recommendations in our report help to get it back on track – for the sake of all citizens who desperately need the NHS to get well soon.”

Recommendations:


The Department for Health is being urged to consider:

Whether more new hospitals should commence construction sooner using pre-existing approaches to design and contracting.

Start construction before the end of 2025 on replacements for the seven entirely RAAC hospitals.

Aim to be ready to start construction during 2024 of at least one early scheme that uses its standardised hospital design, with a particular focus on trialling new clinical infrastructure such as standardised operating theatres.

Amend its Minimum Viable Product version of Hospital 2.0 so it does not result in future hospitals that are too small, and should set out clearly how these future hospitals fit into its assessment of total required hospital capacity nationally and by region.

Avoid reducing planned capital investment to meet day-to-day spending needs in future

Latest news

Ridge buys rival consultant Jubb

Acquisition will see 100 new staff join Ridge
4 hours ago

Enabling works to start £130m Huyton town centre regen

Phase one includes a new council HQ, hotel and 72 flats
5 hours ago

Grainger build to rent pipeline rises to £1.4bn

Rental specialist buys sites in Sheffield and Cardiff to build 600 rental homes
5 hours ago

Kier wins Cambridgeshire County council estate upkeep

Firm will provide building and M&E services to 106 buildings across the county
4 hours ago

Louvres and solar shading specialist files for administration

Hampshire based ALPS lodges court notice after 25 years in business
5 hours ago

Speedy Hire posts a loss in latest results

Hire giant confident of better performance in next six months
5 hours ago

Esh to lead next phase of Riverside Sunderland regeneration

Infrastructure work will allow further development of Sheepfolds area
4 hours ago

Green light for £1.3bn Edinburgh coastal town revamp

First phase of Granton Waterfront scheme will see Cruden Homes create a new community
22 hours ago

Vistry chief operating officer steps down

Earl Sibley exits as his COO role axed for more direct reporting to CEO
1 day ago

House builder Camstead goes into administration

Work stopped on three current sites
2 days ago

Death of piling legend Roger Bullivant

Industry innovator dies after long illness aged 85
1 day ago

ESS Modular went down owing suppliers £7m

Modular specialist owned by ISG owner Cathexis
1 day ago

Builders back farmers in inheritance tax protest

"A rethink is desperately needed" say National Federation of Builders
1 day ago

Willmott Dixon wins £36m leisure centre upgrade

Work to start on historic Westminster 1930s Grade II listed Seymour Centre
1 day ago

Graham wins £100m Cardiff Crossrail phase 1

Work on route to Cardiff Bay to start before end of next year
2 days ago

Laing O’Rourke appoints new European MD

Peter Lyons to take-up new role in February
3 days ago

Profits dip at Stepnell ahead of demerger

Turnover and secured workloads up ahead of restructure
3 days ago

HS2 green bridge deck takes shape

100m-wide wildlife bridge to carry hedgerows and country lane over HS2
2 days ago

1,000-home Wolverhampton city centre scheme in for planning

ECF and council advance City Centre West build to rent scheme
3 days ago

Sisk clinches £54m North London council HQ revamp

Haringey's iconic Grade II listed civic centre to be brought back into use
3 days ago

Ofgem approves £2.5bn Eastern Green Link 1

Work to start next Spring on cable project from Scotland to the north of England
3 days ago

Anglian Water hunts for £1bn delivery partner

Programme delivery partner wil integrate with client team over 15-year plan
3 days ago

Hadden collapse costs supply chain £6.7m

"Highly unlikely" subcontractors will receive anything for their unpaid invoices
3 days ago

Management buyout at M&E specialist

£25m turnover Kimpton in second MBO in its 60-year history
3 days ago

BAM finalises £71m deal to replace first major RAAC school

Work to start on new St Leonards Catholic School in Durham
3 days ago

Scaffolder hit by two tonne weight at nuclear plant

Court hands out £633,000 in fines after Dungeness B decommissioning incident
3 days ago

Go-ahead for 860,000 sq ft East London medical campus

Whitechapel Road scheme of six new and repurposed buildings
3 days ago

Site labour rates hit record high as cost inflation returns

Industry's biggest payroll firm says rates rose nearly 5% last month in London
6 days ago

Morris & Spottiswood acquires part of ISG fit-out division

ISG Cathedral acquisition saves 111 jobs and expands presence across England
7 days ago

New work drives Q3 construction output uplift

Third quarter activity up 0.8% despite slowdown in September
6 days ago

Contractor services