The work covering construction and rehabilitation of concrete and asphalt airside infrastructure covers Manchester, East Midlands and Stansted airports and will be delivered in a 5-8 year programme.
The airport group is looking for a single firm to fill each of the five lots up for grabs, with each lot covering a spend of £44m and £185m. Reserves will also be appointed.
MAG Airfield Framework |
Lot Number |
Regional |
Scope of work |
Lot 1 – Design
(Value: £51m) |
National |
Asset condition surveys to support rehab and renewals decisionsPrinciple Designer provide RIBA 1,2 early concept design
Develop RIBA 3, 4 detail design for specific packages, as required. |
Lot 2 – Pavement Quality Concrete
(£187m) |
National |
Complete construction of or rehabilitation of airside infrastructure including taxiways, stands, aprons and runways |
Lot 3 – Asphalt(£81m) |
National |
Complete construction of or Rehabilitation of airside infrastructure including taxiways, stands, aprons and runways with Marshall asphalt |
Lot 4 – Airfield Ground Lighting
(£44m) |
National |
The removal, replacement, upgrading and maintenance of AGL lighting and infrastructure |
Lot 5 – Planned Renewals and Reactive Support
(£185m) |
Local to
each airport |
Complete planned renewals currently delivered under the hotspots annual award through SMW Framework. |
Click here to register to bid. PQQs need to be in before the end of January with awards expected by August this year.