Wood Transmission and Distribution Limited has been fined £240,000 after a man was left paralysed from the chest down after falling from an electricity pylon during demolition work.

An HSE photo of the accident scene
An HSE photo of the accident scene

Gavin Pugh, from Bangor in North Wales, was 35 at the time of the incident and employed as a linesman by Wood Transmission and Distribution Limited. He had been demolishing and replacing electricity pylons in East Staffordshire when he fell more than 30 feet on 6 April 2022.

Birmingham Magistrates Court was told how Pugh and his colleagues began working on a pylon known as Tower AE11 in preparation for its demolition.

They were unaware there had been previous work to loosen the bolts on the tower, known as “bolt cracking”, undertaken by another team of linesmen. This work had not been risk assessed and there were no systems in place to effectively record and communicate what they had actually done.

In addition, the team that was sent to site that day was also under-staffed for the work being carried out. As the job progressed, Pugh unknowingly attached his fall protection lanyard to a diagonal steel section that was only securely bolted in place at its uppermost fixing.

As he moved around the tower, the steel section he was attached to dropped into a vertical position, causing his lanyard to fall loose, resulting in him falling to the ground. He spent six months in hospital and has been left unable to work as a result of his extensive injuries.

An HSE investigation found that Wood Transmission and Distribution Limited failed to ensure that the work at height was properly planned, appropriately supervised, and carried out in a manner that was, so far as was reasonably practicable, safe.

The company had not considered the work at height hierarchy as part of its planning and had not assessed the risks associated with bolt cracking. Furthermore, it had not adequately resourced the task in line with its own safety documentation, and had failed to put in place a process for transferring work between teams and ensuring safety critical information was recorded and communicated effectively.

Wood Transmission and Distribution Limited of Knutsford pleaded guilty to safety breaches and was fined £240,000 and ordered to pay costs of £14,142.

HSE Inspector Robert Gidman said: “This tragic incident could have been prevented had Wood Transmission and Distribution Limited put in place adequate arrangements to protect its workers from harm.

“Proper assessment of the risks and consideration of work methods, adequate staffing, and clear procedures for transferring towers between teams could have enabled this work to go ahead without incident.

“Instead, because of the company’s shortcomings, a worker has sadly and unnecessarily been left paralysed.”

Latest news

Vinci Building and FM arms rack up big losses for second year

Inaugural consolidated accounts for all Vinci UK operations slip into the red
4 hours ago

Plan lodged for two Birmingham student towers

Sama plans nearly 2,000 student rooms in 48 and 41 floor buildings at Lancaster Circus
4 hours ago

Galliford Try delays annual results announcement

Accountants want more time to go through books
4 hours ago

CITB urged to give everyone a say over need for levy

Consensus process slammed as a "charade"
5 hours ago

Subcontractors wanted across north London

Constructionline event to highlight work opportunities: Register now
4 hours ago

Latest construction hotspots appear outside London

Research reveals fastest growing areas for contract awards
4 hours ago

Bachy Solentanche rejigs business in new growth plan

Business split into two regional and a major projects division
6 hours ago

BAM, Arup and Amey win £2bn Network Rail contract

Largest single contract by value ever awarded by Network Rail.
3 days ago

Luton airport £2.4bn expansion decision delayed

Application decision deadline pushed back 3 months to January 2025.
3 days ago

Plan in for 2m sq ft Hertfordshire data centre campus

Proposed £3.75bn construction project near M25 would sustain 500 jobs
3 days ago

Balfour Beatty wins £363m electricity grid upgrade job

Work to start next year on 29km Bramford to Twinstead high voltage project
3 days ago

Winchmore wins £10m brickwork package with Lovell

Specialist will lay nearly 1m bricks on Thamesmead job
3 days ago

Green light for £125m Camden student scheme

Work to start later this year on site next to iconic Roundhouse
3 days ago

Strong revenue and profit growth puts Kier on firm footing

Revenue recovers to £4bn again with profit ahead almost a third to £68m
4 days ago

Galliford Try steps-in to build £57m Banwell bypass

New contractor found after original winner Alun Griffiths walked-away from job
4 days ago

Hotel M&E specialist Gallant files administration notice

Gallant Building Services is working on hotel, flats and care home projects
4 days ago

Torsion to deliver £43m Leeds student scheme

Construction to start next month on latest project for joint venture
4 days ago

Go-ahead for London Barbican office to flats project

London developer Hub aims to create over 170 co-living homes
5 days ago

Traditional builders dominate £800m MMC framework

20 out of 22 places on modular housing deal go to local contractors
5 days ago

Dubai contractor sells 15% stake in Costain

ASGC sells stake for £38m after investing £25m in fund raise four years ago
5 days ago

Amazon to invest £8bn in hyperscale datacentres

Data centre sector heats up as cloud computing giant AWS unveils big expansion plans
5 days ago

Plan lodged for Square Mile’s fifth tallest tower

54-floor 99 Bishopsgate tower will provide 1 m sq ft of office space
5 days ago

Morgan Sindall pulls off contracts league double

Firm swoops to top monthly and 12-month contracts league rankings
6 days ago

Hadden Construction goes into administration

66 jobs lost at £30m turnover Perthshire contractor
6 days ago

McAleer & Rushe wants to meet subcontractors across Scotland

Register now for Meet the Buyer event: Full list of suppliers wanted
5 days ago

Construction output slide in July ends two-month growth spurt

Recovery stutters along as construction activity dips 0.4%
5 days ago

Laing O’Rourke finance chief to join plastic products firm

Rowan Baker to join Essentra in November
5 days ago

Tight cost control returns Laing O’Rourke to profit

Group margin back to 1.9% as orders swell to record £10.8bn
6 days ago

Kier to noise-proof 20,000 homes around Heathrow

Eight-year programme will involve new windows, doors, loft insulation and upgrade ceilings
6 days ago

Caddick to build £42m Schneider Electric factory

New facility at Scarborough Business Park will open next year
7 days ago

Contractor services