Soaring costs at London incinerator job force M&E rethink

Aaron Morby 1 month ago
Share

Spanish contractor Acciona’s massive incinerator project in North London has been hit by spiraling costs and delays.

Civils work packages have largely completed at the Edmonton energy from waste incinerator project
Civils work packages have largely completed at the Edmonton energy from waste incinerator project

The Energy Recovery Facility forms part of the wider North London Heat and Power Project in Edmonton where costs have soared from £1.2bn to £1.5bn, due to construction material and wage inflation.

The EFR project is now at a critical stage with steelworks due to start shortly and main M&E works to follow.

But supply chain problems have forced Acciona to rethink its procurement strategy for the critical M&E stage of works.

Client body, the North London Waste Authority, representing seven councils, has revealed that the project originally due to be commissioned in 2025 will now be completed in 2027.

While civils works have proceeded well, officials from NWLA are concerned the M&E phase works could hit out-turn costs further.

The programme director for NWLA revealed Acciona has faced problem securing and mobilising subcontractors for the mechanical and electrical sections of the ERF build.

He added that the contractor was reviewing its approach to packaging tasks, to respond to feedback from potential subcontractors. The NWLA is now demanding a ‘realistic schedule and delivery plan.’

He said: “Acciona have identified issues in their delivery of the next stages of the design, procurement, and construction of the ERF facility, namely the mechanical and electrical sections of the build, in what is a challenging period for the construction industry.

“Officers are in regular discussions with Acciona to understand both how on-site momentum can be restored and how future delays can be minimised.

“Acciona are considering as part of this revising their approach to packaging work to generate increased interest from the potential supply chain.”

He added: “Our contract with Acciona provides that delays in the programme are their risk, and they may be liable to pay damages if the new facility is not delivered on time.

“However, it is not in the Authority’s interest to be working with a contractor facing significant financial challenges.”

The value of work completed so far has hit £790m with a Resource Recovery Facility to receive and transfer  waste and EcoPark House visitor centre completed on budget.

The remaining cost to complete is forecast at £730m.

The programme director said: “Until officers are satisfied of the robustness of Acciona’ s schedule and delivery plan, caution must be applied to the certainty of the costs and contingency, although the figures above represent current best estimates.”

 

Latest news

Henry Boot looking to new boss to boost construction

Construction turnover down as division behind schedule winning work
1 hour ago

Billington to expand Shafton works as order book swells

Low steel prices tempt clients to bring stalled projects to the market
56 mins ago

Network Plus Services doubles profit to £32m

Turnover at private equity-backed business tops £500m
1 hour ago

Coroner in training call after scissor-lift tragedy

Practical rescue training needed after worker crushed to death
17 hours ago

Deal to re-start £37m Burnley flood defence job

VolkerStevin/Jacobs' Padiham scheme stalled when costs doubled
2 hours ago

Big public procurement shake-up put back to February

Government delays Procurement Act go-live date by four months
1 hour ago

Architecture boss joins Caddick as Design Director

Former DLA Architecture director Jason Clarke to boost contractor's design offering
11 hours ago

Vinci Building and FM arms rack up big losses for second year

Inaugural consolidated accounts for all Vinci UK operations slip into the red
1 day ago

Plan lodged for two Birmingham student towers

Sama plans nearly 2,000 student rooms in 48 and 41 floor buildings at Lancaster Circus
1 day ago

Galliford Try delays annual results announcement

Accountants want more time to go through books
1 day ago

CITB urged to give everyone a say over need for levy

Consensus process slammed as a "charade"
1 day ago

Subcontractors wanted across north London

Constructionline event to highlight work opportunities: Register now
1 day ago

Latest construction hotspots appear outside London

Research reveals fastest growing areas for contract awards
1 day ago

Bachy Soletanche rejigs business in new growth plan

Business split into two regional and a major projects division
1 day ago

BAM, Arup and Amey win £2bn Network Rail contract

Largest single contract by value ever awarded by Network Rail.
4 days ago

Luton airport £2.4bn expansion decision delayed

Application decision deadline pushed back 3 months to January 2025.
4 days ago

Plan in for 2m sq ft Hertfordshire data centre campus

Proposed £3.75bn construction project near M25 would sustain 500 jobs
4 days ago

Balfour Beatty wins £363m electricity grid upgrade job

Work to start next year on 29km Bramford to Twinstead high voltage project
4 days ago

Winchmore wins £10m brickwork package with Lovell

Specialist will lay nearly 1m bricks on Thamesmead job
4 days ago

Green light for £125m Camden student scheme

Work to start later this year on site next to iconic Roundhouse
4 days ago

Strong revenue and profit growth puts Kier on firm footing

Revenue recovers to £4bn again with profit ahead almost a third to £68m
5 days ago

Galliford Try steps-in to build £57m Banwell bypass

New contractor found after original winner Alun Griffiths walked-away from job
5 days ago

Hotel M&E specialist Gallant files administration notice

Gallant Building Services is working on hotel, flats and care home projects
5 days ago

Torsion to deliver £43m Leeds student scheme

Construction to start next month on latest project for joint venture
5 days ago

Go-ahead for London Barbican office to flats project

London developer Hub aims to create over 170 co-living homes
6 days ago

Traditional builders dominate £800m MMC framework

20 out of 22 places on modular housing deal go to local contractors
6 days ago

Dubai contractor sells 15% stake in Costain

ASGC sells stake for £38m after investing £25m in fund raise four years ago
6 days ago

Amazon to invest £8bn in hyperscale datacentres

Data centre sector heats up as cloud computing giant AWS unveils big expansion plans
6 days ago

Plan lodged for Square Mile’s fifth tallest tower

54-floor 99 Bishopsgate tower will provide 1 m sq ft of office space
6 days ago

Morgan Sindall pulls off contracts league double

Firm swoops to top monthly and 12-month contracts league rankings
6 days ago

Contractor services