M&E subcontractors prices rising faster than other trades

Aaron Morby 3 weeks ago
Share

Specialist M&E subcontractor prices are rising faster than all other trades despite a slowdown in overall construction activity.

A new survey of over 150 subcontractors released by Southern Construction Framework reveals that build costs for the M&E sector rose 7% in the second quarter compared to the previous year.

M&E packages, which account on average for around 20% of project construction costs, continue to face challenges such as high-profile insolvencies, a shortage of skilled labour and rising copper prices.

The survey which covers mainly public sector work in the south of England also blames increasingly complex specifications for upward cost pressure.

Changes driven by stringent environmental and quality requirements are adding to the complexity of M&E solutions.

Supply chains are seeing a rise in the use of PV, air-source heat pumps, ground-source heat pumps, and mechanical ventilation, all driving the complexity of M&E solutions.

These changes have knock-on effects, which are not always immediately clear.

Heat pumps typically require larger ductworks than gas boilers, which can in turn change other design aspects. Similarly, accurately sizing basements, where many of these services are stored, is important and a source of risk.

In addition, fire regulations and local planning requirements have further tested the viability of schemes, with sprinkler systems, fire/smoke dampers, fire hydrant tanks, and electrical vehicle charging points being increasingly utilised.

Adrienne Turner, Framework Manager at SCF, said that these changes to regulation have pushed developers to scrutinise work more carefully, and design more exhaustively. Designing for the worst case has higher costs.

She said: “With M&E being a critical package for projects, and responsible for a high proportion of the construction costs, any unexpected escalations can often place significant pressure on project affordability.

“Costs for the M&E sector are increasing for a myriad of reasons, including labour shortages and changes in specification, following stringent environmental and quality requirements.

“So, it’s vitally important that cost escalations are well understood and predicted.

“Contractors must engage earlier with specialist M&E suppliers to ensure benchmarked rates and that cost allowances are accurate and reflect the designed solution.”

The report also found that despite a decrease in offcial construction output figures, tender workloads actually increased by 3.8% in the second quarter of 2024, when compared to the previous quarter.

Anecdotal evidence from main contractors and their trade suppliers suggests that subcontractors are being asked to revisit previous tenders in the search of cost savings and specification adjustments as past hyperinflation has led to outdated budgets.

Also the surge in insolvencies means that trusted suppliers are being relied upon heavily for pricing works by main contractors.

As a result, this may be driving tender workload across the industry but not necessarily resulting in an improvement in output.

The trades experiencing the largest increases were: concrete frame (11.67%),  windows (6.81%)  and steelwork (6.71%) specialists.

Latest news

Cala Group sold for £1.35bn

Investment groups including former owner sign deal
2 hours ago

Balfour Beatty fined £285,000 after scissor lift death

Court hears how crane pushed over platform killing one worker and seriously injuring another
21 hours ago

House builders fail to get seat on New Towns Taskforce

Policy and planning experts dominate Rayner New Towns Taskforce
2 hours ago

Timber roof dropped in flagship HS2 station design rethink

New Curzon Street aluminium panel design offers better fire safety and cheaper upkeep
17 hours ago

Plan in for 4,000 homes at Earls Court in London

£6bn scheme advances for London's largest development site
22 hours ago

Former MD returns to head O’Keefe Construction

Lee Horsley returns to civils specialist to replace Marc Daly
3 hours ago

Luton Town put in plans for new stadium

Construction to be completed by 2027 on new home for football club
21 hours ago

Henry Boot looking to new boss to boost construction

Construction turnover down as division behind schedule winning work
1 day ago

Billington to expand Shafton works as order book swells

Low steel prices tempt clients to bring stalled projects to the market
1 day ago

Network Plus Services doubles profit to £32m

Turnover at private equity-backed business tops £500m
1 day ago

Coroner in training call after scissor-lift tragedy

Practical rescue training needed after worker crushed to death
2 days ago

Deal to re-start £37m Burnley flood defence job

VolkerStevin/Jacobs' Padiham scheme stalled when costs doubled
1 day ago

Big public procurement shake-up put back to February

Government delays Procurement Act go-live date by four months
1 day ago

Architecture boss joins Caddick as Design Director

Former DLA Architecture director Jason Clarke to boost contractor's design offering
1 day ago

Vinci Building and FM arms rack up big losses for second year

Inaugural consolidated accounts for all Vinci UK operations slip into the red
2 days ago

Plan lodged for two Birmingham student towers

Sama plans nearly 2,000 student rooms in 48 and 41 floor buildings at Lancaster Circus
2 days ago

Galliford Try delays annual results announcement

Accountants want more time to go through books
2 days ago

CITB urged to give everyone a say over need for levy

Consensus process slammed as a "charade"
2 days ago

Subcontractors wanted across north London

Constructionline event to highlight work opportunities: Register now
2 days ago

Latest construction hotspots appear outside London

Research reveals fastest growing areas for contract awards
2 days ago

Bachy Soletanche rejigs business in new growth plan

Business split into two regional and a major projects division
2 days ago

BAM, Arup and Amey win £2bn Network Rail contract

Largest single contract by value ever awarded by Network Rail.
5 days ago

Luton airport £2.4bn expansion decision delayed

Application decision deadline pushed back 3 months to January 2025.
5 days ago

Plan in for 2m sq ft Hertfordshire data centre campus

Proposed £3.75bn construction project near M25 would sustain 500 jobs
5 days ago

Balfour Beatty wins £363m electricity grid upgrade job

Work to start next year on 29km Bramford to Twinstead high voltage project
5 days ago

Winchmore wins £10m brickwork package with Lovell

Specialist will lay nearly 1m bricks on Thamesmead job
5 days ago

Green light for £125m Camden student scheme

Work to start later this year on site next to iconic Roundhouse
5 days ago

Strong revenue and profit growth puts Kier on firm footing

Revenue recovers to £4bn again with profit ahead almost a third to £68m
6 days ago

Galliford Try steps-in to build £57m Banwell bypass

New contractor found after original winner Alun Griffiths walked-away from job
6 days ago

Hotel M&E specialist Gallant files administration notice

Gallant Building Services is working on hotel, flats and care home projects
6 days ago

Contractor services