ISG administrator finds just £35m to pay down £1.1bn debt

Aaron Morby 4 months ago
Share

ISG administrators have warned they will only recover £35m from cash and assets out of the rubble left behind from the collapse of the £2.2bn turnover contractor.

It means there will be no cash for trade contractors owed at least £308m.

The group is now confirmed to have sunk with total debts of £1.1bn, much of this from complex intercompany debt, cash owed to trade creditors and more than £100m owed in tax.

A new report from administrator EY reveals the firm was about to report a staggering £148m in contract writedowns in overdue accounts for 2023 that recorded a £133m pre-tax loss.

Administrators have also given an official account of the chain of events that started to see the top five contractor teeter and finally sink into administration.

They reveal that as far back as 2020, ISG trading and cash performance was being impacted by large loss-making contracts in high-rise residential projects where significant additional time and higher costs were required to deliver.

The firm was also rocked by the cancellation of a £600m Hollywood Sunset Studio job and the termination of a £300m gigafactory contract for British Volt.

By late 2023 with over £100m in dispute on its projects, ISG found it was struggling to obtain performance bonds and found clients demanding cash-backed bonds for projects squeezing cashflow even further.

In October last year a winding up petition from a subcontractor owed £70,000 spooked the insurance market despite being paid straightaway.

This petition prompted a credit insurer to remove cover for multiple suppliers stoking wider concern about ISG’s financial stability.

Around this time, dwindling cash reserves forced ISG to seek extended terms to pay a £60m VAT bill hanging over it.

By January 2024, the situation had deteriorated further and ISG decided it would have to sell its profitable fit-out business or secure a cash injection from its US owner Cathexis.

Accountant EY was engaged to approach potential buyers worldwide and secured interest from 11 private equity and trade buyers.

But this sale process was halted when ISG received an offer for the group from Antipodean Holdings, led by South African entrepreneur Andre Redinger.

By July this year, the legal documentation for the deal was at an advanced stage, but Antipodean then informed Cathexis it was encountering difficulties in transferring funds from South Africa into the UK, citing regulatory approvals in South Africa and banking process-related delays.

On 2 September Antipodean dropped its offer to just £1 but maintained its commitment to fund working capital needs.

Cathexis accepted the reduced offer as the only solvent outcome for creditors and requested evidence that Antipodean had the necessary funds.

Due to lack of progress, ISG’s board halted talks with Antipodean and decided to reopen talks with one of the most interested buyers for ISG Fit Out.

After accelerated talks, this buyer dropped out because of concern about whether critical contracts could be novated.

Other firms were hastily approached but no potential buyer could be found within the tight time frame.  A main sticking point was unpaid group VAT for which ISG Fit Out was jointly and severally liable.

At the same time, Cathexis confirmed its own refinancing process would fail to release necessary funding in the near term. With nowhere to turn ISG directors decided to appoint administrator EY on 20 September.

At the time of the collapse there were 100 live construction sites and 500 live fit out and retail sites being worked on.

 

Latest news

Deck falls off huge scissor lift at Winvic site

Two men seriously injured as platform plunges to the ground
9 hours ago

Bouygues seals deal for £119m Cardiff college campus

Construction to start in June on two new buildings
11 hours ago

Bid race starts for £15bn schools framework refresh

DfE throws framework open to more contractors
17 hours ago

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
1 day ago

London Mayor calls in blocked 600-bed student scheme

Refused 20-storey London PBSA block may still be built
16 hours ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
1 day ago

Arrest after pedestrian death on construction site

Tragedy during site preparation works for new Wigan car park
17 hours ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
1 day ago

Planning green light for Sheffield warehouse site

Existing factories to be demolished in new scheme for Rula Developments
17 hours ago

New rail property company to unlock land for 40,000 homes

First four sites released in Newcastle, Cambridge, Manchester, and Nottingham
2 days ago

Drainage specialist Subscan files administration notice

Specialist employing 131 people files court notice
2 days ago

Four win Network Rail £300m engineering design deal

Eastern region deal will include design for Northern Powerhouse Rail
2 days ago

Funding go-ahead for Banwell bypass after fresh cost hike

Galliford Try contract rises £14m to £64m after final design change
2 days ago

Graham wins Southport £75m Marine Lakes Centre

Firm replaces Kier which parted ways with backer Sefton Council
2 days ago

Chancellor unveils extra £2bn capital spend a year

Construction promised a defence dividend in military base and homes upgrade work
2 days ago

McLaren confirms subcontractor team on £135m warehouse job

Work starts on TN2 Gateway site in Kent.
3 days ago

Vistry profits slump after site costs reporting debacle

House builder launches internal whistle-blowing service in business culture review
3 days ago

Severfield chief to step down

Alan Dunsmore to leave structural steel group by end of June
3 days ago

Funding hurdle remains as Lower Thames Crossing gains consent

Government claims £9bn project may start in 2026 as private finance options explored
4 days ago

Mace wins £600m Euston Tower overhaul

1970s tower's foundations and core to be retained as floor plates extended
3 days ago

Summer start for main works on London green tower

Axa sanctions start at 50 Fenchurch Street 36-storey office block
3 days ago

Japan’s leading flats builder JVs with L&G for UK push

Partners plan to build over 1,000 rental homes in London
3 days ago

Wates submits plan for 1,000 homes Harrow council scheme

Former civic centre Poets' Corner site kicks off housing partnership
3 days ago

Morgan Sindall upgrades forecast for next 12 months

Overbury fit-out arm gets off to a flying start in 2025
4 days ago

Restructure underway at Henry Boot Construction

New management team restructures business after drop in turnover
4 days ago

Government pledges £2bn stop-gap funding for 18,000 homes

Funding avoids cliff-edge in social housing delivery before new grant programme agreed
4 days ago

Just two major new roads schemes to start this year

National Highways sets out one-year interim spending plan after RIS3 delay
4 days ago

Plans go in for £400m GRAHAM Manchester site

Demolition and enabling works underway with main construction set to start next year
4 days ago

Building safety levy rate set at up to £10,000 a home in London

Levy introduction pushed back a year to Autumn 2026 - list of new rates
4 days ago

BAM wins £100m revamp of Broadgate Tower in London

Front of tower 3-storey extension to use cross laminate time and re-used steel
5 days ago

Contractor services