London Super Sewer now fully connected

Aaron Morby 2 months ago
Share

After ten years of construction, London’s super sewer tunnel has been finally hooked up to the original Victorian infrastructure.

Light at the end of the 7.2m diameter tunnel running along the Thames
Light at the end of the 7.2m diameter tunnel running along the Thames

Engineers have completed the last of 21 connections with the new 25km Thames Tideway Tunnel.

The project is not yet fully complete, as it will still need to be tested in storm conditions over the coming months.

It is being hailed as a major civil engineering success. Originally, the project was due to be completed by 2024 at an outturn cost of £3.5bn.

The impact of Covid pushed the project back to 2025 with the outturn cost now set to be £5bn.

Under its pioneering Regulated Asset Base model the developer’s construction risk is shared with consumers, a financing model that will now be used to deliver the Sizewell C nuclear power station.

Tideway CEO Andy Mitchell said: This is another significant step forwardwith this final connection complete, the super sewer is fully up and running and protecting the Thames.

“Our next step is to test it in storm conditions which is why we are keeping a close eye on the weather and we will do this over the coming months.”

Andy Mitchell has been with the vast project since 2014

He added: We are at the start of a new chapter for London and its river. Our mission has always been about creating not just a tunnel, but a healthier, thriving environment for the river and its inhabitants.

Work on the project began in 2016 – with activity taking place at two dozen construction sites from Acton in west London to Abbey Mills Pumping Station in Stratford, east London.

More than 20 deep shafts – some as wide as the dome of St Paul’s Cathedral – were constructed across London to divert sewage flows and to lower tunnelling machines into the ground.  

The first of these giant machines started work deep beneath London in 2018, with primary tunnelling on the 25km main tunnel and two smaller connection tunnels completed in 2022. 

By the autumn of 2023, a secondary tunnel lining was fully complete on all the tunnels, with the heavy civil engineering work then completed in the spring of 2024.

Latest news

Driver escapes injury as scaffold collapses onto van

Major three-lift scaffold fall blocks north London high street
4 days ago

Gilbert Ash to be sold to staff

£267m turnover contractor to transition to an Employee Ownership Trust
5 days ago

M Group seals biggest-ever deal with Telent takeover

Digital infrastructure specialist deal lifts turnover to £3bn
5 days ago

Aggregates firm Ashville went down owing more than £3m

Debts revealed in Companies House update
4 days ago

Cardo saves 100 jobs at Breyer roofing arm

Private equity-backed Welsh maintenance group continues to expand
5 days ago

Excavator knocked off lorry going under bridge

Traffic Commissioner inquiry after accident in south London
4 days ago

Czech energy tycoon buys UK’s biggest rebar supplier

Spanish offload Celsa UK operation to be rebranded 7 Steel UK
5 days ago

Caddick Construction targets £400m turnover

Regional shake-up pays off at contracting arm
6 days ago

Redrow chief steps down after Barratt merger

Matthew Pratt leaving after 22 years
6 days ago

United Living names new property services senior team

New CEO and COO appointed to lead growth in housing upkeep and retrofit
5 days ago

Wynne triples turnover in three years to over £90m

Five-year growth strategy pays off
5 days ago

Speedy Hire blames Budget for branch closures

National Insurance rises accelerate closure programme
5 days ago

Builder gets suspended sentence for Covid loan fraud

M&E specialist inflated turnover to claim maximum loan
5 days ago

Scores of M&E firms win places on £400m CHIC framework

Axis Europe and Seddon secured spots on social housing deal
7 days ago

Coroner hears how worker was crushed under digger

Inquest opens into tragedy at Rose Builders site
7 days ago

Billington lowers 2025 forecast amid pricing pressure

Tender prices under pressure due to project delays and cancellations
6 days ago

Willmott Dixon lands Dover town centre revamp

Alliance agreed to regenerate several key council sites
1 week ago

Go-ahead for London City office-to-flats scheme

Hub's 150 Minories job in Aldgate to create 280 co-living homes
1 week ago

Wates mobilises as £200m Middlesbrough scheme approved

Gresham Street scheme includes a hotel, 240 flats and over 400 student rooms
1 week ago

Crashed M&E contractor TNA owed supply chain £7m

Sister company buys assets including company vans
1 week ago

Renaker eyes bumper 2025 despite Gateway 2 concern

Strong construction pipeline to support another record year
1 week ago

Wessex Water picks civils firms for £65m framework

Over 40 smaller firms will support AMP8 civils spending programme
1 week ago

Green light for nearly 400 flats at Leeds scheme

Three blocks up to 18 storeys approved at Armley Road
1 week ago

Subcontractors wanted across South London

Work up for grabs from main contractors and clients: Register now for Constructionline event
1 week ago

Heavy lorry ban on Severn Bridge as cables deteriorate

Crossing "not designed and built for today’s levels or weight of traffic"
1 week ago

Muse submits Oldham town centre regeneration plan

Plan advances for six sites to deliver 2000 homes, an hotel and office space
1 week ago

Construction returns to growth after two tough months

Concern grows Trump turmoil is spooking property investors
1 week ago

Skanska wins £43m Clifton Bridge deal

Contractors says scheme is a "complex project that will be delivered to tight timescales"
1 week ago

Green light for 44-storey Manchester resi tower

Developer Glenbrook to start hunt for main contractor
2 weeks ago

Ten win £670m Network Rail eastern region small works deal

CK Rail, QTS, Colt and Construction Marine pick up two lots
2 weeks ago

Contractor services