Piling firm in plea to major contractors over lead times

Grant Prior 10 years ago
Share

Piling specialist Aarsleff is calling on Tier 1 contractors and clients to factor in longer lead times in a bid to avoid project delays.

Aarsleff said current lead times are coming under pressure as the construction recovery continues and specialist contractors are struggling to cope.

Chris Primett, MD Aarsleff (UK) Ltd, said: “Whilst it is great to see signs of recovery within the construction sector, the demand this presents on a finite pool of resources, positions occupied by the specialist contractor such as piling, is considerable.

“The ability to adapt to the rate of contracts available is not an easy one and has the potential to ultimately present itself on-site.”

Lead times for many materials  are already being stretched with some block manufacturers quoting four months and longer for deliveries.

Primett said: “Any delays can cause problems on-site but they could also threaten the rate of the UK’s recovery and possibly lead to swings in the price of construction products and services as a consequence of supply and demand.

“As well as a better appreciation by Tier 1 contractors and clients that longer lead times may be needed, there must also be a better understanding of the effects moving previously programmed start dates can have on a specialist contractor, as this might have quite a significant impact, especially for any follow-on-projects that may have been committed to.

“Piling, as the work of specialist contractors, has always been considered a long lead-time element and where these appear on the construction time-scale or pathway, they should be given due consideration and scheduling so that any delays do not to impact on the entire project.”

Aarsleff is also keen to to point out that specialists can also do a lot to ease the problems themselves.

Primett said: “It is important that specialist contractors clearly identify lead times and communicate these to clients from the outset of discussions.

“This will allow projects to be planned better, with works scheduled and front-end elements like piling and ground works may even benefit from early contract placement to protect the entire project and remove them as the rate limiting step for future works on the construction pathway.”

Latest news

Resi developer Sheen Lane heading for administration

Richmond based firm has a turnover of £50m
2 hours ago

Building safety act adding six months to delivery times

New approval gateways slow student room development programmes
1 hour ago

Five contractors win £550m airfield framework deal

MAG picks team for Manchester, Stansted and East Midlands airports
1 hour ago

Galldris bounces back to strong profits

South east civils specialist gets trading margin up to 11%
1 hour ago

Management buyout at Midlands contractor

Family business GI Sykes sold to management
1 hour ago

Taylor Woodrow wins Wolverhampton city centre revamp

£19m contract will last two-and-a-half years
1 hour ago

Morgan Sindall contracts league champion for second year

Kier ranks second in closely contested race between majors
1 day ago

New Year layoffs as Scottish modular house builder collapses

East Ayrshire Connect Modular falls into administration
1 day ago

Thames Water bidders day for £2.2bn reservoir scheme

Tenders to be invited in October for new Abingdon reservoir in Oxfordshire
1 day ago

Buckingham Plant Hire quits heavy kit market

Firm to sell fleet and focus on lighter, sustainable plant
2 days ago

Clients ‘ignoring building safety’ reforms

Clients still subjecting contractors to aggressive and sub-economic pricing
1 day ago

Castleforge plans expansion after £100m data centre deal

Investor moves into booming data centre market
1 day ago

Construction output growth drops to six-month low

Subcontractor rates rise at fastest rate for 18 months
2 days ago

Suir Engineering swoops for Scottish M&E contractor

Irish M&E firm launches UK expansion with Taylor & Fraser acquisition
2 days ago

Aggregates supply firm files administration notice

Ashville Aggregates and Concrete operates across London and South East
2 days ago

Plans in for 44-storey Manchester resi tower

Developer Glenbrook to appoint contractor this year
3 days ago

Briggs & Forrester names new engineering services MD

Will Newman replaces Ian Lawrence who steps down after eight years
2 days ago

Morgan Sindall bags Salford Uni acoustics building

Planning submitted for Acoustics Building at Crescent Innovation area
2 days ago

Lambeth to release six sites for £250m homes plan

Call for development partner to deliver 450 mixed tenure homes
2 days ago

Adrian Speller joins brother as joint MD of Midlands builder

Speller Metcalfe boosts senior leadership team
3 days ago

Winner unveiled for £2.9bn aqueduct revamp

Construction costs for Haweswater Aqueduct rise to £2.9bn from £1.75bn
5 days ago

Fortem and Equans face fight for £3bn housing upkeep deal

Birmingham City Council aims to sign new 10-year deals for four regions
3 days ago

Lendlease strikes deal to sell UK construction arm for £35m

US private equity firm Atlas to finalise purchase deal by summer
7 days ago

Hercules to offload suction excavator arm

Fleet of 30 trucks generates around £5m revenue a year
3 days ago

Tarmac trials new technique to cut concrete road noise

Quieter trips for drivers and longer-lasting roads
3 days ago

HS2 set for “fundamental reset” to lower construction costs

New chief executive promises action after latest project update
1 week ago

Solar panel installer fined £120,000 after roof fall

Court hears how employee broke his leg in fall
1 week ago

Network Rail chief Andrew Haines knighted

Thin pickings for construction in this year's New Year Honours
1 week ago

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
2 weeks ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
2 weeks ago

Contractor services