BAM facing extra £31m Cambridge busway claim

Aaron Morby 10 years ago
Share

BAM Nuttall is facing further claims of up to £31m to fix remaining defects on Cambridgeshire’s troubled guided busway.

The civil engineering contractor paid the county council £33m last year in an out-of-court settlement, which included defects known about at the project’s completion date.

But a new technical report has outlined the need for up to £31m of extra repairs not uncovered at the time of the settlement.

A second legal battle would come at an awkward time for BAM Nuttall. The parent Dutch Group is presently reviewing the UK and German business as part of an £80m cost-cutting drive.

BAM was two years late in handing over the project and originally claimed the council owed them around £70m more than the £84m contract price. But the settlement saw the council pay the original contract value with BAM footing the difference.

The latest technical report for the council outlines that some parts of the guided busway were either not built to the agreed design or don’t comply to national standards specified in the contract.

Report’s findings of further defects

• Shims and neoprene pads were put in without being fixed so they now slip and cause movement of the beams, effecting ride quality.
• Foundations were not deep enough as outlined in national guidelines on certain sections so they could move in the clay conditions.
• Inadequate drainage at two locations
• Joints between the guideway beams that were too narrow to allow for thermal expansion of the beams.
• Some bearings were identified as being out of position.
• Beams not being restrained enough by brackets so they move.

Bob Menzies, Service Director, Strategy and Development, said: “The technical and legal advice is that these defects were created or left by the contractor and they should be fixed.

“More importantly this should be paid for by Bam Nuttall.

He added: “The Busway is a highly successful transport system that reached its passenger targets early and is used for millions of journeys.

“We have fixed some of the defects but the advice is if we leave them then beams could move seriously effecting ride quality. The Committee will look at this independent expert advice and make a decision on the best way forward.”

The council has estimated costs of £5.3m for a fresh legal battle with BAM Nuttall over the latest problems, but hopes the dispute will not reach court.

Councillors will hear that the legal advice believes BAM is in breach of contract and that the Council has a good case and should pursue the contractor for the money to pay for the necessary repairs.

A decision on how the council will proceed will be taken on Tuesday.

Latest news

Resi developer Sheen Lane heading for administration

Richmond based firm has a turnover of £50m
4 hours ago

Building safety act adding six months to delivery times

New approval gateways slow student room development programmes
3 hours ago

Five contractors win £550m airfield framework deal

MAG picks team for Manchester, Stansted and East Midlands airports
3 hours ago

Galldris bounces back to strong profits

South east civils specialist gets trading margin up to 11%
3 hours ago

Management buyout at Midlands contractor

Family business GI Sykes sold to management
3 hours ago

Taylor Woodrow wins Wolverhampton city centre revamp

£19m contract will last two-and-a-half years
3 hours ago

Morgan Sindall contracts league champion for second year

Kier ranks second in closely contested race between majors
1 day ago

New Year layoffs as Scottish modular house builder collapses

East Ayrshire Connect Modular falls into administration
1 day ago

Thames Water bidders day for £2.2bn reservoir scheme

Tenders to be invited in October for new Abingdon reservoir in Oxfordshire
1 day ago

Buckingham Plant Hire quits heavy kit market

Firm to sell fleet and focus on lighter, sustainable plant
2 days ago

Clients ‘ignoring building safety’ reforms

Clients still subjecting contractors to aggressive and sub-economic pricing
1 day ago

Castleforge plans expansion after £100m data centre deal

Investor moves into booming data centre market
1 day ago

Construction output growth drops to six-month low

Subcontractor rates rise at fastest rate for 18 months
2 days ago

Suir Engineering swoops for Scottish M&E contractor

Irish M&E firm launches UK expansion with Taylor & Fraser acquisition
2 days ago

Aggregates supply firm files administration notice

Ashville Aggregates and Concrete operates across London and South East
2 days ago

Plans in for 44-storey Manchester resi tower

Developer Glenbrook to appoint contractor this year
3 days ago

Briggs & Forrester names new engineering services MD

Will Newman replaces Ian Lawrence who steps down after eight years
2 days ago

Morgan Sindall bags Salford Uni acoustics building

Planning submitted for Acoustics Building at Crescent Innovation area
2 days ago

Lambeth to release six sites for £250m homes plan

Call for development partner to deliver 450 mixed tenure homes
2 days ago

Adrian Speller joins brother as joint MD of Midlands builder

Speller Metcalfe boosts senior leadership team
3 days ago

Winner unveiled for £2.9bn aqueduct revamp

Construction costs for Haweswater Aqueduct rise to £2.9bn from £1.75bn
6 days ago

Fortem and Equans face fight for £3bn housing upkeep deal

Birmingham City Council aims to sign new 10-year deals for four regions
3 days ago

Lendlease strikes deal to sell UK construction arm for £35m

US private equity firm Atlas to finalise purchase deal by summer
1 week ago

Hercules to offload suction excavator arm

Fleet of 30 trucks generates around £5m revenue a year
3 days ago

Tarmac trials new technique to cut concrete road noise

Quieter trips for drivers and longer-lasting roads
3 days ago

HS2 set for “fundamental reset” to lower construction costs

New chief executive promises action after latest project update
1 week ago

Solar panel installer fined £120,000 after roof fall

Court hears how employee broke his leg in fall
1 week ago

Network Rail chief Andrew Haines knighted

Thin pickings for construction in this year's New Year Honours
1 week ago

Staff stunned as engineering consultancy Clarkebond closes

Firm was only bought three months ago by rival Independent Design House Group
2 weeks ago

Vistry issues third profit warning in three months

Profit expected to fall £50m below forecast due to delayed completions
2 weeks ago

Contractor services