Vinci faces major loss on Nottingham Tram project

Aaron Morby 10 years ago
Share

Vinci is scaling down UK construction activity as it battles with losses on the late-running Nottingham Tramlink project.

The project was due to be completed by the end of the year.

But sources have told the Enquirer that an Easter handover date is now being looked at once final testing is complete.

The delay would leave Vinci facing a heavy bill for liquidated damages that could run into tens of millions of pounds including labour and materials cost overruns on the £423m project.

Officially the team working on the project has told Nottingham Council that the project will be completed some time in the first half of next year.

Vinci said it had implemented a policy of reducing bidding for UK projects while the new management team focusess on completing its £232m civils element of the project.

Sources have told the Enquirer that some completed work on the delayed tram project has had to be ripped out and redone.

Several subcontractors have decided not to continue on the job.

An army of around 1,500 people is now understood to be battling to get parts of the phase two project finished.

Vinci said it expected to complete construction before the end of the year and it was working with its joint venture partner, concessionaire and other stakeholders to complete commissioning work to enable commencement of a full service as soon as possible.

The French contracting group warned that it had run into problems with several contracts in the UK after issuing a trading statement for the third quarter.

It said: “In the UK, problems with several projects, mainly the Nottingham tram extension, prompted the new management at VINCI plc to scale back activity.”

Investor relations director at Vinci Construction Christopher Welton  said: “Our new management team is in place and concentrating on getting the problem project out of the way before they turn to developing new business.

“We don’t know what the exact timing of that will be.”

He said that voluntary scaling down of UK activity was responsible for an £80m fall in revenue in the third quarter.

Losses on the Nottingham Tramlink project will be a blow to Vinci’s UK construction business which has suffered losses of £34m and £7m in the last two years of reported accounts for its building arm.

Its civil engineering business, built from the former Taylor Woodrow civils arm, had escaped such problems remaining in profit as it grew rapidly in recent years from around £150m to close to £400m.

Earlier this month, the French boss of Soletanche Freyssinet Bruno Dupety was parachuted in to run Vinci Construction UK after chief executive John Stanion retired and managing director Andrew Ridley-Barker suddenly left the firm.

 

 

Latest news

Breyer Group files administration notice

Staff hope rival firm could buy assets and save jobs
51 minutes ago

Former Severfield director takes helm at Embrace Steel

New CEO Martin Kelly aims to step up expansion of steelwork contractor
1 hour ago

£302m upgrade funding awarded to FE colleges – list

Cash shared out between England’s 179 college groups
51 minutes ago

FK Facades thrives but construction arm hit by ISG row

Dispute with failed contractor costs specialist £5.5m
2 hours ago

Galliford Try gets go-ahead for Milton Keynes PRS tower

33-storey tower needs gateway 2 approval before work can start
20 hours ago

Small house builders get £150m funding for green homes

Developers will have to meet-up to ten new criteria to benefit from interest rate discounts
1 hour ago

Lendlease Construction renamed Bovis

US private equity firm completes £35m purchase of UK contracting business and rebrands
1 day ago

Breyer Group battles for survival as rivals circle

Housing maintenance firm fights three winding up petitions in a month
1 day ago

Careys facing £2.4m claim by developer over demolition cartel

Giant Hong Kong developer claims it was overcharged on Lots Road Power Station job
1 day ago

Multiplex profit drops a third as revenue rises to £780m

Spate of new orders sets contractor up for three years of work
1 day ago

Galliford Try and Breheny land latest Sizewell C road deals

More infrastructure deals for new nuclear power station
2 days ago

Worker trapped in collapsed septic tank pit

Contractor and director fined after worker suffers multiple fractures
1 day ago

Homes England buys stalled Broad Marsh site

Demolition to finally be completed as developer hunt begins
2 days ago

Vistry go-ahead for 353 homes at Rochester Riverside

Work to start on next phase of Kent town regeneration at end of this year
2 days ago

M&E firm J S Wright collapsed owing £19m

Trade creditors hit for £11.4m by employee-owned Midlands firm
2 days ago

Right to work checks to be extended to self-employed

Government plans crackdown on illegal working and rogue employers
2 days ago

Midlands developer turns to London with £1bn resi schemes trio

SevenCapital plans 1,000 flats in Kensington, Islington and the Isle of Dogs projects
2 days ago

Deck falls off huge scissor lift at Winvic site

Two men seriously injured as platform plunges to the ground
5 days ago

Weston targets Build to Rent with new division

Weston Partnerships signs first deals with asset managers and councils
2 days ago

Bouygues seals deal for £119m Cardiff college campus

Construction to start in June on two new buildings
5 days ago

£140m cash injection to speed-up flood defence schemes

Funding part of £2.65bn investment over the next two years
2 days ago

Bid race starts for £15bn schools framework refresh

DfE throws framework open to more contractors
5 days ago

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
6 days ago

London Mayor calls in blocked 600-bed student scheme

Refused 20-storey London PBSA block may still be built
5 days ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
6 days ago

Arrest after pedestrian death on construction site

Tragedy during site preparation works for new Wigan car park
5 days ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
6 days ago

Planning green light for Sheffield warehouse site

Existing factories to be demolished in new scheme for Rula Developments
5 days ago

New rail property company to unlock land for 40,000 homes

First four sites released in Newcastle, Cambridge, Manchester, and Nottingham
6 days ago

Drainage specialist Subscan files administration notice

Specialist employing 131 people files court notice
6 days ago

Contractor services